Weekly Management Reports
Date: 2008-03-03
Accompishments
* Completed "Choose Game Mode" component (Matt)
* Completed Alpha of "Game Window" component (Casey)
* Finished tower placement function (Mark)
* Fixed crash when enemies had no path (Tyler)
* Fixed crash when enemies reached end of path (Tyler)
Goals & Priorities
Short Term -
hold integration meeting to finalize Stage 1 integration
- Primary : Tyler
- Due : 03/08
attend integration meeting with Prototype Team
- Primary : Casey
- Due : - 03/08
Complete "Game Window" component of GUI for Stage 1 release.
- Primary - Matt
- Due - 03/10
Complete Game Logic for Stage 1 Release
- Primary - Mark
- Due - 03/10
Long Term
Web Hosting for Stage 1
- Primary - Tyler
- Due - 03/14
Beta testers for Beta version of TD
- Primary - Casey
- Due - 03/14
VVR v1
- Primary - Mark
- Due - 03/14
Finalize decisions regarding game content, design, and format for Stage 2
- Primary - Matt
- Due - 03/24
Needs
None