Weekly Management Reports
Date: 2008-02-18
Accompishments
* Completed SDS v2 (Matt)
* Completed SDS v2 (Casey)
* Completed prototype (Tyler)
* Completed prototype (Mark)
Goals & Priorities
Short Term
* implement initial Flash GUI (Matt due 2/25)
* implement initial Flash GUI (Casey due 2/25)
* work on prototype 2.0 (Mark due 2/25)
* work on prototype 2.0 (Tyler due 2/25)
Long Term
* Beta version of TD (Mark Due 03/10)
* Beta version of TD (Casey Due 03/10)
* Beta version of TD (Tyler Due 03/10)
* Beta version of TD (Matt Due 03/10)
* Beta testers for Beta version of TD (Casey Due 03/7)
* Finalize decisions regarding game content, design, and format (Matt Due 03/24)
* Finalize decisions regarding game content, design, and format (Tyler Due 03/24)
* Finalize decisions regarding game content, design, and format (Mark Due 03/24)
* Finalize decisions regarding game content, design, and format (Casey Due 03/24)