Weekly Management Reports

Date: 2008-04-14

Accompishments

Worked on XML scoreboard (Tyler)
Fixed game play bugs and started adding graphics (Mark)
Fixed GUI bugs, added keyboard shortcut commands (Matt)
Fixed GUI bugs, fixed graphics alignment for some enemies (Casey)

Goals & Priorities

Short Term
Continue work on high score web server
Primary: Tyler Due: 4/18
Continue adding functionality to game, fixing bugs, adding graphics,
Primary: Mark Due:4/18
Continue adding functionality to GUI, and adjusting game play
Primary: Casey Due:4/18
Continue adding functionality to GUI
Primary: Matt Due:4/18

Long Term
Finish up web server backend for high scores
Primary: Tyler Due:4/25
Make game not look like crap
Primary: Mark Due:4/25
Continue to read and respond to Beta-Tester feedback
Primary: Casey Due:4/25
Finish brochure Documentation
Primary: Matt Due:4/25

Needs

none